Contractor Fraud · Disability · Dream Homes Nearly Famous Rebuilding Blog · Foundation systems · House raising and Moving · Kathleen Dotoli, Esq. · Monmouth & Atlantic County · Nearly Famous Rebuilding Seminar · New Homes & Rebuilds in Ocean · New Homes & Rebuilds in Ocean, Monmouth & Atlantic County · New homes and elevations in Monmouth County · New Homes and elevations in Ocean County · Pilings · Pilings - Helical versus timber · Rebuilding · Rebuilding, House raising and Moving, Pilings, Renovations · Renovations · RREM Path B · RREM Seminars · Worker's Compensation

Dream Homes Renovation, Rebuilding & Elevation Blog – 8-11-17 – Tips for Change Orders & Sanity – Rebuilding Seminar 8-16-17 Tuscan Bistro – Decks and Railings – New Modular & Design Studio

Dream Homes and Development Corp.

Dream Building LLC.

Atlantic Northeast Construction LLC

Nearly Famous Rebuilding, Renovation, and Elevation Blog

8-11-17

Hello Sandsters –

I hope today finds you well and enjoying your summer.

Today I have some helpful items for you. Change orders in chaos systems like elevation projects and the inherent delays are discussed in more detail. We remind you about our next Rebuilding Seminar which is this Wednesday, August 16th, live at Tuscan Bistro and streamed on the internet on Facebook Live. We talk about the Toms River Home Show on October 28 & 29th at the Pine Belt Arena in Toms River, where we’ll be exhibiting.

I again included the article on decks & rail from last week’s blog since we received a lot of positive response, affects almost everyone and was helpful to many people. Finally, we again mention our new Dream Homes Jersey Proud Design Center at 2109 Bridge Avenue in Point Pleasant, where you can see modular home plans, kitchens, baths, flooring and tons of fixtures.

Nearly Famous Rebuilding Seminar This Wednesday August 16th, 2017

See us in person and or watch us on Facebook Live!

Our next Rebuilding Seminar will be held this Wednesday August 16th, 2017 from 6 pm at the Tuscan Bar and Grill on Hooper Avenue in Toms River, across from the Ocean County Mall. We’ll be joined by Kathleen Dotoli, Esquire, Jason Devooght (Devooght House Lifters) and Scott Lepley, architect. We’ll also be streaming it on Facebook Live and be online if you want to email questions or comments while the seminar is under way. We had over 30 people join us on Facebook at the last seminar and were able to take questions from people who couldn’t make it to the seminar, which was an excellent addition to our program.

If you are planning a project, whether a new home, elevation or renovation, make sure you attend for helpful information from our excellent speakers. It will help you get started on the right track. We focus on homeowners that are early in the rebuilding process, and haven’t completed design work, or chosen a builder or architect.

We’ll talk about architectural and engineering planning, construction technique, RREM guidance, help with choosing the right builder and consumer safety cautions when dealing with him, financing your project, comments and tips about home elevation and finally advice on how to buy a new home or sell your existing one. We also talk about RREM issues, (the lunacy of) managing your own project, the money builders really make on your project and ways to avoid delays and going over budget.

So, mark the date and call 609 693 8881 or 732 300 5619 to reserve your space if you want to attend. Refreshments will be served and space is limited.

Permit fees, Design & Hiring Your Own Architect: Generally, permit fees are paid by the homeowner, since they can’t usually be determined at the start of a project. Design & architectural fees are usually itemized separately and are (for us) a pass-through cost. In other words, we oversee the entire design process and it costs our clients the same (usually much less) amount of money than if the homeowner deals with the architect directly. This also results in significant savings in both construction design and redesign fees. Remember – the person who is going to build the project should be involved in the design from inception, so practical best practices can be designed in from the start.

Perspective and Sanity: (Partial repeat – See last blog): I’ve written about this subject many times in the past, but as with many simple concepts, it bears repeating. Simply put, issues that come up during the construction of your project are not worth losing your mind, health or sanity over. These issues include delays, code changes, additions made during your project and any other unknown occurrence that may cause you stress.

Change Orders & Additions in Chaos Systems: Today we’ll give a few tips about change orders in chaos systems and the resulting inevitable delays.

First, it’s common when renovating or even building a new home, to want to add items or make changes to what’s already been decided. It’s sometimes impossible (especially with elevations and renovations) to visualize exactly what your home will look like in 3 dimensions from a plan and as your project progresses, it’s natural to want to tinker with the scope of work.

There is nothing at all wrong with making changes or additions while under construction. I mention this point because many builders will not accept change orders once a project has begun. Many charge per change order.

Second, it’s very important to accept that any building project larger than a deck or a bathroom remodel, is by its nature, a chaos system.

Chaos systems have many moving parts. There are separate, distinct categories, some of which move in a linear, critical path manner (when Step 2 can’t happen before Step 1 is completed) and some of which progress independently and can occur concurrently while other parts of the project are progressing.

Every step is subject to many random variables. These include tool and equipment breakdown, delay in supplies being delivered, sickness and other tragedy, and township inspection or review delays, among many other factors. However, the single most common reason for delay in any chaos system is changes made during the process (at least in a chaos system). A chaos system is affected in numerous ways by a single change.

(This is otherwise known as the Butterfly Effect, where a butterfly flaps it’s wings in China and we have a hurricane in Los Angeles).

So, what’s the moral of the story?

Changes cost money and inevitably cause delays. The cost portion is easily understood but the delay aspect is something most homeowners do not realize when they make changes. Changing a single item in a residential project usually affects 3-5 other items which may not be immediately evident. An average change, depending on complexity, will add a week or more to a schedule. Structural and mechanical changes can add a month.

Making a deck 4’ larger requires a new plot plan, zoning permit application, additional concrete footings, possibly an additional exterior outlet, and additional bolt requirements for added size.

Adding a door requires a new header of the door, a new switch and exterior light, possibly new stairs to the ground and a concrete or paver pad outside the door.

Installing 5 more outlets in a basement requires a permit update, a new breaker in the electrical panel, a new electrical schematic for the township and a site survey to determine possible conflict with other mechanical or structural components.

Deciding to add 3 courses of block to a foundation requires a new plot plan, a new engineering plan and submission of both, sheetrock under the floor, additional lights and an additional smoke detector (with electrical plan update) and a larger door to the crawl/basement.

You get the idea.

Suffice to say that all changes in your project will affect other items and will cause delay.

Again, there’s nothing wrong with changes if you understand that delays to the overall project are an inherent part of the process.

There are some thoughts to consider when considering changes.

About Dream Homes: Dream Homes & Development Corp. (OTCOB: Ticker DREM) is a publicly traded, fully reporting (audited) company with main offices in Forked River and a Modular Design Center in Point Pleasant. We’re the only public company doing home elevation work in New Jersey. Please view us online – if you like us and believe in what we’re doing, we would love to have you as shareholders. For more information and an information package, contact Matt Chipman, our investor relations person. Matt can be reached at (818)923-5302, (310) 709-5646 or matt@GreenChipIR.com. You can view our operational results and financials at any time at www.sec.gov.

Decks, more decks and railing…Decks are one of the more popular improvements and one of the easiest ways to add value to your home. Decks fall into 3 main categories – pressure treated, composite and fiberglass. Railings can be pressure treated, vinyl rail or glass.

Pressure treated decks and rails are the most economical but require a certain amount of maintenance (or not) to keep the appearance constant. Or not (if you’re like me). Maintenance is simple and involves applying Thompson’s Water Shield or some other preservative once every few years. P/T decks are also subject to shrinking, swelling and fading. You should expect to pay somewhere in the range of $40 – $50 per square foot, including footings, framing, decking and rails. Add an additional $5 per square foot for vinyl rail instead of pressure treated.

Composite decking (Trex or other) with vinyl rail are easily the most popular choice over the last decade or so. We’ve become a maintenance free society, we’re aging as a populace and few people want to bother keeping up with the maintenance a pressure treated deck requires. Composite decking comes in many colors and brands – just the Trex brand alone has 3 product lines, with the Transcend line being very high end and including wood grains and exotic colors. All styles are installed with hidden hangers so no nails can be seen (except for stairs). Expect to pay between $50 – $60 per square foot, including footings, framing, decking and rails. Add an additional $3-$5 per square foot for upgraded styles and quality levels, instead of entry level composite decking.

Fiberglass decking is the choice when you want to create a waterproof space under the deck. It’s very useful to create outside patio space where you can linger when it’s raining. It does get hot and eventually must be gel coated after 5-7 years as it may start to crack in places. It comes in many colors. Installation is much more complicated, since a solid floor must be built, the floor must have a pitch for water runoff, and the fiberglass itself is installed in a 3-stage process. The price difference for fiberglass alone is $12 – $15 per square foot, and other than omitting the decking, all other framing is the same. Fiberglass is usually not done on stairs. Expect to pay between $60 – $70 per square foot, including footings, framing, decking and rails.

Railing generally falls into 3 categories – pressure treated, vinyl and glass or wire. Vinyl is the most popular choice and is most often paired with composite decking. Glass is increasingly popular and can be used selectively (for cost savings) for areas facing the water. Expect to pay $60 – $70 a running (linear) foot extra for glass rail. Vinyl and pressure treated railing are generally included in the prices I listed above, but are generally $45 – $65 and $25 – $35 a linear foot, respectively is priced separately from the deck costs.

New Beach Bungalow on your lot from $89,800!! See last 2 blogs for more detail. Note: This model is perfect for many small lots in the shore area including Ocean Beach, Lavallette, Ortley and South Seaside Park.

Most general contractors and builders are unwilling to provide turn-key elevation/renovation projects. It’s messy, requires diverse skill sets and deep administrative support and places all responsibility for everything directly on the builder’s shoulders. Dream Homes regularly perform turn-key renovation and design build projects and will remain as one of the best, solid companies in the years to come.

Why does this matter to you? If a company isn’t committed to being in the line of work for which you are contracting, they will not support it correctly during and after the project. That means less resources (personnel and otherwise) devoted to your project. Currently at Dream Homes, we’ve been actively hiring carpenters, helpers, marketing and support staff for 2 years. We’re committed to the elevation /renovation business and improve every single day – our commitment to provide additional, better resources to our clients is ongoing.

Moral of the story: Try and avoid working with any company not committed to the type of project you are undertaking. Ask to see current projects in process or being started.

Need to Phone a Friend? Need a Rescue? 2017 Scheduling & Priority projects – If you’re stuck in a stalled project for whatever reason (contractor in jail or indicted, bankrupt, lazy, inept, no money, etc.) we’ll help you with a prompt evaluation of your situation. We do consultation and estimates immediately for projects that are stuck. It doesn’t change what happened to you in the past, but at least you’ll know how to get back on track, without chasing someone for a month to get an initial meeting and written estimate. As a note, often we’re the only company willing to finish projects that have been abandoned.

New Dream Homes Modular Division – Design, Kitchen & Bath Studio –

Come see our Dream Homes Jersey Proud Custom Modular design studio at 2109 Bridge Avenue in Point, with complete kitchen, flooring & modular home design studio. See Lou Obsuth, who has a wealth of experience in modular construction as well as kitchen and bath design.

Kathleen M. Dotoli, Esquire – Consumer Protection: Kathleen is a workers’ compensation and disability attorney in Toms River and speaks regularly at our Rebuilding Seminar. Kathy gives an excellent presentation about consumer protection that will save you money and grief. (Next one is Wednesday, August 16th, 2017). Email Kathy at kmdotoli611@aol.com or call her office at 732 228 7534 for a copy of her seminar presentation.

Mission Statement and Comment: At Dream Homes, we’ll help you when no one else will. We regularly handle messy and unpleasant real estate, construction and renovation situations. We do the projects that few other people can do, and help people finish and get back in their homes. If you’re stuck and can’t figure out how to proceed, call us and we’ll do our best to help you.

At Dream Homes, we believe that taking on difficult unpopular projects is part of the social contract we have with the community and the Jersey Shore. We’ve never abandoned a client or failed to finish a project – we feel very strongly that it is our obligation to help Sandsters and others in need.

Video & Past Seminars

Photos & Videos – Click on the link below

https://blog.dreamhomesltd.com/video-photo/

Future Homes & Townhomes for Sale: We’re actively working on the development approvals for several properties in Bayville and Forked River.

Dream Homes at Tallwoods: We’ll be offering 13 beautiful new 3 and 4-bedroom single-family homes for sale in the mid $200,000 range in late 2017 / early 2018.

Dream Homes at the Pines: 58 new 2-3 bedroom townhomes, with garages. Anticipated opening in spring / summer 2018.

If you’re looking for new homes this year or early next year, give us a call and we’ll get you information.

There’s Real…and then there’s Memorex…What an Estimate and Scope of Work is Supposed to Look Like…  

https://blog.dreamhomesltd.com/2017/01/28/dream-homes-rebuilding-blog-1-27-17-shore-house-lifters-indicted-a-real-scope-of-work-rebuilding-seminar-hometown-hero-rrem/

Click on the link above or call us and we’ll send you a blank scope of work for your reference.

Yeah, We Do That for You… This was an excellent article from the 1/8/17 blog, which received positive response from many people. If you missed it, go back and read it now at https://blog.dreamhomesltd.com/2017/01/08/dream-homes-nearly-famous-rebuilding-blog-1-8-17-why-use-dream-homes-yeah-we-do-that-for-you-hometown-hero-award-in-brick-rebuilding-seminar-1-18-16/

Definitions & Important Considerations That Can Delay Your Project: Click on the link below

https://blog.dreamhomesltd.com/definitions/

References & Testimonials – Click on the link below

https://blog.dreamhomesltd.com/references/

Remember – if you have a specific question, send me an email or a text. Don’t wait for a seminar or a site visit to clarify a point. Whether you are a Dream Homes client or not, I’ll always try and help you or guide you in the right direction. If you’ve sent an email or left a voice mail and haven’t received a response, try and contact me again. Messages are lost occasionally.

Note to Sandsters: Though I write this blog and hold the seminars to help guide homeowners through the maze that is any reconstruction project, Dream Homes does what I write about. Dream Homes & Development Corp. and Dream Building LLC are new home builders and general contractors who are actively renovating and reconstructing projects up and down the shore. We supervise and manage elevation projects & house moves, demolish and build new homes, and develop and build entire new neighborhoods. In the past 23 years, we’ve completed over 1500 new homes, 190 elevation projects and 500,000 square feet of commercial buildings. 28 of our elevation projects have been rescue projects, where we came in to save a homeowner when someone else left. Dream builds new homes, demolishes existing damaged homes, elevates and move homes, complete additions and renovations and rescues homeowners when their other contractors abandon them. We work with private clients as well as Path B clients in the RREM program. Call, text or email to set up an appointment for a free estimate on your rebuilding project.

That’s all for today Sandsters. I hope my words helps you move forward. As always, call or write with any questions.

Regards,

Vince Simonelli

Dream Homes & Development Corp. (OTCQB: DREM)

Dream Building LLC

Atlantic Northeast Construction LLC

New Home Builder #045894

Home Improvement Contractor #13VH09325600

Home Improvement Contractor #13VH07489000

Office: 314 S. Main Street

Mailing: PO Box 627

Forked River, NJ 08731

Office: 609 693 8881 F: 609 693 3802 Cell: 732 300 5619

Email: vince@dreamhomesltd.com

Website: www.dreamhomesltd.com

Blog: http://blog.dreamhomesltd.com

Twitter: #foxbuilder

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s